Foundation
Scrape |
DHTMLGoodies.com00. This Slideshow illustrates the JM1065 Instructions pages 8 - 10
../../../RGT_Website_assets/ajax-loader.gif
DHTMLGoodies.com
01. The Foundation is assembled (link for Foundation Assembly is at left)
01D.png
DHTMLGoodies.com
02. The line for the left side of the stair position will become usedful
02D.png
DHTMLGoodies.com
04. View from the back: Base Floor, lined up on the back and left edges
04D.png
DHTMLGoodies.com
05. Adjust the Foundation as necessary to make it line up
05D.png
DHTMLGoodies.com
07. Page 9: The Gable Left Side glues behind the Gable Front
07D.png
DHTMLGoodies.com
08. Lined up top, bottom, on the edge, and at the grooves
08D.png
DHTMLGoodies.com
16. The outside face lines up with the stairhole tracing
16D.png
DHTMLGoodies.com
17. The Lower Right Front glues to the face of the Gable Right Side
17D.png
DHTMLGoodies.com
20. The Lower Right Side glues to the right edge of the Lower Right Front
20D.png
DHTMLGoodies.com
21. Clean the Mid Floor and grooves (see "Scrape" at left)
21D.png
DHTMLGoodies.com
24. Lift so the wall's glue doesn't smear while inserting into the grooves
24D.png
DHTMLGoodies.com
26. Lined up in back, straighten and support with Dividers
26D.png
DHTMLGoodies.com
38. the Top Floor lines up with the outsides of the walls
38D.png
DHTMLGoodies.com
43. Tape tightly in both directions for a corner that won't slip
43D.png
DHTMLGoodies.com
44. Recheck all the corners, adjust if necessary, tape in both directions
44D.png
|